Practical railway engineering. Depots and Workshops


Proper maintenance of rolling stock

Any railway relies upon proper maintenance of both its rolling stock and its infrastructure to ensure that efficient and reliable operation is sustained.

Both operational and maintenance considerations need to be fully taken into account at the planning stage and should be monitored in the first years of operation to check that assumptions were correct and procedures are adequate. Failure to do this could result in a steadily declining standard of satisfaction.

Designers and engineers must discipline themselves to revisit installations or systems to see for themselves how things have actually worked out in practice This is common sense but the need to do this cannot be over stressed and applies to all disciplines. The author has visited many railway systems around the world and could cite examples where consultants have repeated mistakes on new railways simply because they did not check experience gained on other similar installations. Similarly, all those engaged in design in any field need to consult and draw on the ‘real life’ experience of manufacturers, operators and maintainers.

There are many examples of this but just one is given. Deficient sliding door gear is one of the most frequent reasons for taking rapid transit stock out of service. Designers need to understand in this area for instance what usually causes the failures and how often they occur, how passengers’ action contributes to the failures, what the operators have to do to rectify matters in the immediate term and how quickly faults can be rectified.

Apart from the obvious economic considerations, lack or deterioration of adequate maintenance of rolling stock will have a progressively adverse effect on the following:

• Safety

• Customer satisfaction and co-operation

• Customer perception of reliability

• Availability — this will influence the total number of trains that are necessary in the fleet for a given level of service

• Morale and ‘pride’ of operating staff

Rolling stock maintenance considerations

Generally speaking, maintenance of rolling stock can be divided into two main categories, planned and unplanned or more usually known as routine and casualty. In the area of planned routine maintenance activity the following can be included:

• Preparation for service

• Routine examination

• Cleaning

• Renewal of consumables (such as brake pads, light bulbs, upholstery cushions etc)

• unit exchange

• major mechanical overhaul

In the routine completion of all these activities, operators and engineers need to co-operate to establish the best layout, sequence of events and frequency for every activity involved.

Establishing a maintenance regime

Every railway needs to establish for itself a regime for the regular maintenance of rolling stock. The various activities, involving both inspection and work to components, will necessitate some time when stock is not available for normal operation. It is difficult to get the balance right between over and under maintenance and this must be watched carefully, allowing suitable adjustments to be made in both procedures and frequencies when these are shown to be necessary.

With a new railway, or with entirely new stock on an existing railway, the following factors should be taken into consideration when establishing a maintenance regime initially:

• experience with similar stock on other railways,

• manufacturers recommendations,

• theoretical wear and fatigue deterioration of replaceable components e.g., brake linings etc,

• climatic conditions i.e., extremes of heat, cold, or wet,

• degree of heavy use e.g., extreme crowding of passengers or carriage of very heavy and abrasive materials,

• required comfort/cleanliness standards for passengers concerned e.g., First Class overnight long distance travellers would expect a higher standard than short distance suburban Standard Class commuters, perhaps.

It is essential that all those involved in maintenance are provided with reliable and up to date information. Staff need to be adequately trained and be provided with the necessary maintenance manuals. Of equal importance is the necessity to keep accurate up to date records of every maintenance activity on each item of rolling stock so that the full history of each vehicle is properly documented. In the past this activity was a laborious but necessary ‘chore’, but with the advent of the computer the keeping of such records should be much easier.

Maintenance management

Having established a maintenance regime each railway system will need to set up an organisation for adequately managing the maintenance process and monitoring it. Up until very recent years it has been traditional on most railways to maintain rolling stock ‘in-house’. This involved extensive workshops and proportionately large labour forces but it did have the effect of keeping control within the parent organisation. In this case however, the size of the workforce and the workshop plant and facilities needs to carefully match the actual demand or it will be inadequate if too small or unduly costly if too extensive. Manpower can be adjusted if demand changes but it is not always possible to modify plant and buildings once they have been installed.

In recent years, much more thought has been given to contracting out certain maintenance operations. This is more flexible if demand changes but does require more control. Many components and units are now made for easy replacement. The replacement of the units can be done in the railway’s own workshops or depots leaving the manufacturers to service or repair their own units and components on a contractual basis. Because of this trend, many railway workshops have either closed or become very much reduced in size.

The balance between workshops and depots

Originally railway companies set up both railway workshops and railway depots on their systems. As practically all the engineering work was done ‘in-house’, the scope of activities was very wide and depots and workshops had very differing functions.

In many cases, the early railway companies manufactured their own locomotives and rolling stock and carried out all major repairs and refitting in the same works. The practice has gradually changed over the years and now most manufacture and major overhaul is carried out by independent suppliers.

Railways therefore need to carefully consider what engineering activities still need to be carried out on their own premises and by their own staff. Having decided this, it is a short step to a decision as to what operations are most sensibly carried out at a depot and which are better done at a separate workshop location.

On many railways, depots contain a minimum of workshop facilities for day-to-day maintenance and unit/component changing, the major work being carried out elsewhere by tendered contract, either by supplier or ‘in-house’.

Depot siting

The siting of depots on any railway system is important and needs to be given careful consideration in the planning stage.

Main line railway operating patterns usually require depots to be as close as possible to termini or to origin/destination points for freight running. There will often be severe constraints at such locations relating to space availability and high land costs. Even so, final locations should be not too far away from the ideal siting as ‘empty running’ costs and times will amount to a considerable sum over a depot lifetime.

Some reduction of these costs can sometimes be effected by stabling trains in sidings or even station platforms closer to the point of operational origin than depots. However this can have disadvantages in that rolling stock will not have full depot facilities available should cleaning, minor overnight servicing or repairs be necessary.

Metros and light railways which serve a city or large conurbation will often have lines or services which originate in outer suburbs, run through the city centre and out to suburbs on the other side, with some converging or at least interchange with other lines or transport modes.

At the beginning and end of the traffic day on such systems traffic demand will fall off, particularly in the outer areas. Because of this some trains will often be reversed before they reach the outer termini, reducing the train frequency in the outer suburbs. This likely pattern of operation needs to be carefully considered before location of depots is finalised on Metros, light railways and other essentially suburban commuter services.

For Metros therefore the most practical location for a depot is often about half to three quarters of the distance out from the city centre. At this point land will be more available, but not too far out for easy access for operating and engineering staff.

At this location, it is also more likely that the potential problems of lack of space, noise, pollution and proximity of neighbours can be overcome.

Another advantage of such a location is that the depot can be double ended. This means that entry and exit to the depot for trains leaving or entering service can be in either direction and at either end. Experience has shown that if a depot has just one point of entry from the running lines, extensive delays and disruption can be caused by just one train becoming immobilised or one set of points failing at the depot entrance. In bad weather also frozen points at one end can completely shut up all the trains in a depot at the commencement of a traffic day.

The needs of the maintainer

Maintenance requirements need to be carefully considered by the designer of rolling stock. All too often stock is designed without any proper appreciation of the needs of the maintainer.

As a guide, the following twelve key requirements must be kept in mind:

1. Good access to components

2. No dust or dirt traps

3. Simple fault finding systems

4* No superfluous equipment

5. High reliability, proven equipment

6. Minimum number of quick release fastenings

7. Easily removable sub-assemblies

8. Small number of tools required

9. Simple isolation of systems

10. All fixings capable of torque tightening

11. Equipment cases watertight

12. Maximum interchangeability of components

As can be seen, a few moments consideration will show that all these requirements are simply ‘common sense’. It is surprising however how often maintainers are thwarted in carrying out simple operations because one of these considerations has been overlooked.

Basic requirements for depots

Each railway must carefully look at the different functions that need to be carried out within the depot. The size of the fleet, diversity of stock type and turn-around of trains will all have a bearing on the facilities required.

The following twelve basic general requirements need to be addressed:

1. Sidings which are adequate to stable the maximum number of trains/ units likely to be in the depot, with adequate access walkways for operating and engineering staff.

2. Adequate provision of point and crossing work and ‘shunt necks’ to enable trains to be moved within the depot to allow proper cleaning and maintenance and marshalling in correct order for service. The layout should preferably be ‘double ended’. Some form of control of points and train movements in the depot needs to be provided.

3. Covered workshops with all necessary cranes/jacks, inspection pits, walkways, equipment, test facilities and etc for maintenance work and lifting. Road access needs to be provided to the workshop area adequate to handle the largest components that will need to be taken away for major overhaul or replacement.

4. Adequate lighting and heating as appropriate.

5. Staff facilities, offices and training rooms.

6. Stores with both road and rail access.

7. Wheel turning facility.

8. Raised bogie roads and bogie wash.

9. Repair facility for painted surfaces.

10. Train washing arrangements for both internal and external surfaces and underframes. Specially constructed wash roads are necessary to enable used water to be properly collected, filtered and channelled away to drains.

11. De-icing arrangements.

12. Fire alarms and protection.

In applying these requirements to any railway system it is advisable to remember that as well as the normal planned and predictable maintenance items of work, there will always also be unforeseen emergency items which will demand urgent work from time to time. If there is no spare capacity in depots, such incidents could cause major disruption to regular maintenance work.

Collision damage may occur from time to time. Also a small amount of local damage might occur to a large number of trains originating from a track or structure irregularity. A good example of this would be damage to wheels through sliding on wet leaves or damage to collector gear due to a displaced current rail ramp or walkway board.

On electrified railways, there may well be other specialised requirements that will need to be provided in railway depots. This will probably include inspection and maintenance of current collection equipment and possibly battery charging and storing.

Performance indicators and audit

It is necessary to establish reliable performance indicators for all classes of rolling stock to ensure that engineers and operators can detect any deterioration in maintenance standards. There must be a continuous search for the optimum maintenance regime that will give the most economic performance overall. It is also essential that a periodic audit is carried out to check independently that standards are being maintained.


Редакторы: Admin
Создано Admin, 22.11.2014 в 13:21
Последнее редактирование Admin, 22.11.2014 в 13:21
0 Комментария , 1062 Просмотров
Похожие темы
Тема Автор Раздел Ответов Последнее сообщение
=Книги= Bonnett C.F. - Practical Railway Engineering Admin Книги и журналы 0 22.11.2014 17:24
[Книга Путь и п/х] The Railway Track and Its Long Term Behaviour: A Handbook for a Railway Track of High Quality (Tzanakakis K.) Admin Библиотека 0 20.04.2014 15:33
Practical railway engineering. Rolling Stock Admin Wiki 0 02.07.2013 07:12
Practical railway engineering. Station Layout Admin Wiki 0 01.07.2013 20:58
Practical railway engineering. Introduction Admin Wiki 0 01.07.2013 20:47

 


Здесь присутствуют: 1 (пользователей: 0 , гостей: 1)
 

Ваши права в разделе
Вы можете создавать новые темы
Вы не можете отвечать в темах
Вы не можете прикреплять вложения
Вы можете редактировать свои сообщения

BB коды Вкл.
Смайлы Вкл.
[IMG] код Вкл.
HTML код Выкл.
Trackbacks are Вкл.
Pingbacks are Вкл.
Refbacks are Выкл.



Часовой пояс GMT +3, время: 20:43.

Яндекс.Метрика Справочник 
сцбист.ру сцбист.рф

СЦБИСТ (ранее назывался: Форум СЦБистов - Railway Automation Forum) - крупнейший сайт работников локомотивного хозяйства, движенцев, эсцебистов, путейцев, контактников, вагонников, связистов, проводников, работников ЦФТО, ИВЦ железных дорог, дистанций погрузочно-разгрузочных работ и других железнодорожников.
Связь с администрацией сайта: admin@scbist.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 
Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2026, Jelsoft Enterprises Ltd.
Powered by NuWiki v1.3 RC1 Copyright ©2006-2007, NuHit, LLC Перевод: zCarot