System:
City population
1,492,000 (2006), forecast 5.25 million by 2020
Developer / operator
Roads & Transport Authority (RTA)
Date opening
Red Line: 2010
Total planned system length
320km by 2020
Design speed (max.)
90km/h
Green: 18 (+2 Red Line interchanges)
Operating hours
Sat-Thurs: 6am to 11pm; Fri: 2pm to Midnight
Estimated investment
$4.2bn
Rolling Stock:
Number of trains required
87 (Red Line: 62 five-car sets, Green Line 25 three-car sets)
Power System:
Power supply
750VDC third rail