key facts
Key Data
Location
Scotland
Name
Airdrie-Bathgate Railway Link
Project manager
Network Rail
Total project cost
£300m (at 2006 prices)
Start date
June 2008
Completed
December 2010
Route
Airdrie- Drumgelloch-Caldercruix- Blackridge-Armadale-Bathgate

The Airdrie-Bathgate Railway Link connects Edinburgh to Glasgow through Bathgate, Drumgelloch and Airdrie. It reopened in 2012.

The route was closed for a period of more than 50 years; it closed to passengers in 1956 and freight in 1982, when the tracks were also removed.

A single track between Bathgate and Edinburgh was reopened in 1986. In 2004, the Scottish Government decided to reopen the line on the recommendations of the Central Scotland Transport Corridor Study.

The study recommended that the line be reinstated to encourage the use of public transport among the local communities and ease traffic on the nearby motorway and road networks, as well as providing better public transport in West Lothian and North Lanarkshire. The Act of Parliament commissioning the project received Royal Assent in May 2007.

The Scottish Government found the project to be economically viable. It expects a return of £1.81 for every £1 spent on it.

Network Rail, the key owner and operator of the UK rail network, managed the project on behalf of Transport Scotland, which funded the £300m project.

The project reopened the link and upgraded the existing Airdrie-Drumgelloch and Bathgate-Edinburgh lines. This resulted in a double-tracked electrified railway line from Glasgow to Edinburgh.

The project

Network Rail and its team of contractors split the construction activity into three stages – advanced works, main works and final works.

"The Scottish Government found the project to be economically viable. It expects a return of £1.81 for every £1 spent."

In the advanced works stage, construction was carried out between Newbridge Junction and Bathgate. This involved an upgrade of the double-track Edinburgh-Bathgate line, and an upgrade for Livingston North and Uphall stations.

The main works stage involved the connection of Edinburgh and Glasgow by the construction of new stations at Armadale and Caldercruix; relocating the stations at Bathgate and Drumgelloch; and laying a double-tracked and electrified line between Bathgate and Drumgelloch stations.

The final works stage involved an upgrade of Airdrie and Livingston North stations.

The £60m contract to construct the Airdrie-Bathgate link was awarded to Balfour Beatty Rail Projects in October 2008. This included the construction of a new track between Airdrie and Bathgate, double tracking the line between Airdrie and Drumgelloch and electrifying the entire route.

During April 2009, Network Rail awarded three contracts worth £80m, £14m and £6m to Carillion, BAM Nuttall and C Spencer respectively. Carillion built the three stations Caldercruix, Armadale and Drumgelloch, and also carried out certain ground treatment and filling activities. The new Bathgate station, new platform at Airdrie, and bridge and earthworks were delivered by BAM Nuttall. C Spencer was responsible for developing the light maintenance depot at Bathgate.

The proposal to construct a new station at Blackridge was approved by the West Lothian Council in March 2009. Network Rail designed and integrated the construction of the station into the project.

Infrastructure

Double tracking of the rail link began in June 2008 and was completed in October of the same year. The construction and upgrades of the railway lines and stations began in late 2008. Work on the rail link between Airdrie and Bathgate began in mid-2009.

The National Cycle Route 75 is a 16km path across central Scotland, developed following the closure of the Airdrie and Bathgate link in 1982. The cycle path was closed in October 2008, to facilitate railway line construction work between Bathgate and Drumgelloch. Network Rail invested £7.3m to construct a cycle path parallel to the railway line, which opened in December 2010.

"Journey time between the terminal stations is 74 minutes."

By December 2009, some 17 bridges had been dismantled along the route, and 14 new ones constructed – this was to allow for double-tracking and electrification along the route. Journey time between the terminal stations, Edinburgh Waverley and Glasgow Queen Street, is 74 minutes. Four trains stop at each station every hour, except for Armadale and Caldercruix, which will only have two services per hour.

A new depot has been constructed at Bathgate station, and a parking lot for 400 cars opened in December 2010. Bathgate, which opened in October 2010, is 150m long and able to accommodate a nine-carriage train, the same design that used for all other stations. It has CCTV that is monitored from a regional control room, cycle storage and park-and-ride facilities.

Drumgelloch station closed in May 2010. It is being relocated to a new site, and is due to open after minor works are completed. The relocation work includes parking space for 358 cars.

Rolling stock

The line uses Class 380 and Class 334 trains. These are used on the Ayrshire, Inverclyde and Renfrewshire routes to and from Glasgow Central, and between Glasgow and Edinburgh via the Airdrie and Bathgate line.

Network Rail runs four trains an hour between Edinburgh and Glasgow during peak hours. Trains run at a speed of 80mph.

"Network Rail runs four trains an hour between Edinburgh and Glasgow during peak hours"

Environmental impact

Scottish National Heritage and the Scottish Environment Protection Agency completed an environmental impact assessment and a landscape and habitat management plan.

The key impact areas of the railway construction were defined and ways to reduce such effects suggested. Network Rail conducted surveys to identify endangered species and has plans for vegetation replanting after construction is completed.

The key environmental benefits of the railway link include electrified lines, reducing carbon emissions; 1,000 parking spaces at stations, encouraging people to park and travel; and a cycle path.

Airdrie-Bathgate rail line

Expand Image Expand Image
The original Airdrie-Bathgate rail line was closed in 1956, but the Scottish Government has now decided to reopen and upgrade the line.

Edinburgh to Glasgow

Expand Image Expand Image
The line will connect Edinburgh and Glasgow, also passing through Drumgelloch on the way.

Airdrie-Bathgate rail line

Expand Image Expand Image
Trains on the Airdrie-Bathgate line will run at speeds of up to 80mph.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the rail industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the railway industry