Key Data:
Operator
Metro Warszawskie
Contractor
Consortium of Asaldi (45%),GГјlermak Isaat (10%) and PBDiM (45%).
Estimated Investment
€800m
Start of Construction
August 2010
Route
Chrzanów in the west to Kondratowicza in the east.
Specific Data:
Existing Lines
Metro Line 1
Length of Metro Line 1
22.6km long with 21 stations.
Rolling Stock
60 Russian and 108 Alstom. 35 more to be purchased.
Current Passenger Capacity
28,000 passengers per day