Ipoh-Padang Besar Section to Finish on Time

06 January 2010


The Ipoh-Padang Besar section of Malaysia's electrified railway double-tracking project will finish on time in 2013 despite delay, according to the country's transport minister.

The 12.485bn Ringgit ($3.69bn) project involves laying of 329km of electrified double tracks from the country's border with Thailand at Padang Besar to Ipoh, capital of Perak state.

The project, which should have been 47.2% complete by November 2009, is running a deviation of 12.8%, according to the minister.

The project is a continuation of the double tracking project from Rawang, north of Kuala Lumpur, to Ipoh, which finished in December 2007.

Work is being carried out by the MMC-Gamuda joint venture consortium.


Post to:

Newsletter Sign-Up
For all the latest news in the rail industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the railway industry